(Draft) Agenda of the Metaverse1 Kick-Off workshop

October 7

Ø 09:00 Welcome and Introduction

Ø 09:45 Consortium changes and impact (overview)

Ø 10:30 Break

Ø 11:00 Start of parallel working groups

Ø WG1: Starting the actual work è Operational Work plan

Ø WG2: Consortium changes and impact è Revision of project plan

Ø WG3: Way of Working è Project Handbook

Ø WG4: Advanced status of the standardization efforts è Input to MPEG-V

Ø 12:30 Lunch

Ø 13:30 Parallel working groups (Cont.)

Ø WG1: Starting the actual work è Operational Work plan

Ø WG2: Consortium changes and impact è Revision of project plan

Ø WG3: Way of Working è Project Handbook

Ø WG4: Advanced status of the standardization efforts è Input to MPEG-V

Ø 15:00 Break

Ø 15:30 Feedback from the Parallel working groups (4 * 15’)

Ø 16:30 Alignment discussion (preparation for WG’s in Day 2)

Ø 17:15 Concluding and plan for second day

Ø 17:30 End of first day

Dinner/ Social event

October 8

Ø 09:00 Parallel working groups (Cont. & Implementing Alignment)

Ø WG1: Starting the actual work è Operational Work plan

Ø WG2: Consortium changes and impact è Revision of project plan

Ø WG3: Way of Working è Project Handbook

Ø WG4: Advanced status of the standardization efforts è Input to MPEG-V

Ø 10:30 Break

Ø 11:00 Parallel working groups (Concluding & Finalizing)

Ø WG1: è Operational Work plan

Ø WG2: è Revision of project plan

Ø WG3: è Project Handbook

Ø WG4: è Input to MPEG-V

Ø 12:30 Lunch

Ø 13:30 Feedback from the Parallel working groups (4 * 20’)

Ø WG1: Starting the actual work è Operational Work plan

Ø WG2: Consortium changes and impact è Revision of project plan

Ø WG3: Way of Working è Project Handbook

Ø WG4: Advanced status of the standardization efforts è Input to MPEG-V

Ø 15:00 Break

Ø 15:30 Detailed planning & action plan ‘active work packages’

Ø WP1 (Use case driven requirements & State of the art overview) (30’)

Ø WP4 (Dissemination, Standardization & Exploitation) (10’)

Ø WP5 (Project Management) (10’)

Ø 16:30 Concluding, Wrap-Up and AOB

Ø 17:00 End of second day and kick-off workshop